Gorgon’s first LNG cargo faces delay

Original article by Angela Macdonald-Smith
The Australian Financial Review – Page: 13 : 3-Aug-15

US-based Chevron has advised that the Gorgon LNG project may not commence shipments until early 2016. Production was initially slated to begin in the September 2014 quarter, but this was subsequently pushed back to late 2015 due to delays and a cost blowout. Chevron executive Jay Johnson says unforeseeable events such as inclement weather could further delay the $US54bn project, which also faces the threat of strike action over enterprise agreement negotiations.