Original article by Peter Ker
The Australian Financial Review – Page: 27 : 17-Apr-25
Rio Tinto shipped just 70.7 million tonnes of iron ore from the Pilbara during the March quarter, which is 17 per cent lower than the last three months of 2024. Production was affected by four cyclones during the period, putting Rio Tinto about 13 million tonnes behind schedule on achieving its full-year target of shipping between 323 million and 338 million tonnes. Rio Tinto expects to incur mitigation costs of about $150m as it seeks to reach the lower end of its guidance. Meanwhile, the Pilbara Ports Authority has advised that 133.62 million tonnes of iron ore was shipped through Port Hedland during the March quarter, an increase of 1.3 per cent year-on-year; Port Hedland is used by BHP, Fortescue and Hancock Prospecting.
CORPORATES
RIO TINTO LIMITED – ASX RIO, PILBARA PORT AUTHORITY, BHP GROUP LIMITED – ASX BHP, FORTESCUE LIMITED – ASX FMG, HANCOCK PROSPECTING PTY LTD