Origin to tip $600m into battery

Original article by Colin Packham
The Australian Financial Review – Page: 17 : 21-Apr-23

Origin Energy stated in February that it will close the Eraring coal-fired power station in 2025, and that it intends to build a battery on the station. Origin has now made a final investment decision to proceed with the $600 million battery, which will have a capacity of 460MW, with the option to increase it to 700MW. At a capacity of 460MW, the battery will have a dispatch duration of two hours; this would increase to four hours at 700MW.

CORPORATES
ORIGIN ENERGY LIMITED – ASX ORG

AGL defies Coalition over Liddell closure

Original article by Angela Macdonald-Smith, Ben Potter
The Australian Financial Review – Page: 1 & 6 : 27-Sep-18

AGL Energy’s interim CEO Brett Redman has reaffirmed its commitment to exiting coal-fired power generation and its proposed closure of the Liddell power station in 2022. However, Redman has told the company’s AGM that AGL will seek to work with the federal government to reduce electricity prices. Relations between AGL and the government became strained under former CEO Andy Vesey over the closure of Liddell, prompting Energy Minister Angus Taylor to warn of potential intervention if electricity retailers do not take action to reduce prices.

CORPORATES
AGL ENERGY LIMITED – ASX AGL, AUSTRALIA. DEPT OF THE ENVIRONMENT AND ENERGY, MACQUARIE GROUP LIMITED – ASX MQG, ENVIRONMENT VICTORIA

Alinta Energy turns up heat on AGL with $250m Liddell bid

Original article by Angela Macdonald-Smith
The Australian Financial Review – Page: 15 : 1-May-18

Ian Myles of Macquarie Group says Alinta Energy’s offer to buy AGL Energy’s Liddell coal-fired power station is "opportunistic", while Mark Busuttil of JP Morgan adds that AGL would be unlikely to consider such a low offer. AGL itself has repeatedly stressed that Liddell is not for sale as the power station will be required until its scheduled closure in 2022, with the site to then be used to generate renewable energy. Alinta recently signalled its intention to make a formal offer to buy Liddell.

CORPORATES
AGL ENERGY LIMITED – ASX AGL, ALINTA ENERGY (AUSTRALIA) PTY LTD, MACQUARIE GROUP LIMITED – ASX MQG, JP MORGAN AUSTRALIA LIMITED, CHOW TAI FOOK ENTERPRISES LIMITED, AUSTRALIA. DEPT OF THE ENVIRONMENT AND ENERGY, MANUFACTURING AUSTRALIA LIMITED

Alinta’s $1bn bid for coal power station

Original article by Ben Packham, Andrew White
The Australian – Page: 1 & 4 : 5-Apr-18

Prime Minister Malcolm Turnbull and Treasurer Scott Morrison have urged AGL Energy to consider selling the Liddell power station, which is slated to close in 2022. Alinta Energy has advised that it is preparing to make an indicative offer of around $A1bn for the coal-fired power plant, and CEO Jeff Dimery is confident that his company can extend the ageing plant’s operational life at a significantly lower cost than AGL has estimated. AGL in turn has argued that it needs to retain Liddell as the site will be used to supply alternative sources of energy beyond the existing plant’s closure.

CORPORATES
AGL ENERGY LIMITED – ASX AGL, ALINTA ENERGY (AUSTRALIA) PTY LTD, AUSTRALIA. DEPT OF THE PRIME MINISTER AND CABINET, AUSTRALIA. DEPT OF THE TREASURY, AUSTRALIAN LABOR PARTY, AUSTRALIAN COMPETITION AND CONSUMER COMMISSION, MACQUARIE GENERATION, AUSTRALIAN ENERGY MARKET OPERATOR LIMITED, CS ENERGY LIMITED, DELTA ELECTRICITY AUSTRALIA PTY LTD, SHANDONG RUYI TECHNOLOGY GROUP COMPANY LIMITED

Watchdog slams AGL on Liddell

Original article by Angela Macdonald-Smith
The Australian Financial Review – Page: 1 & 6 : 14-Sep-17

The Australian Competition & Consumer Commission had opposed the sale of Macquarie Generation – which owned the Liddell and Bayswater power stations – to AGL Energy in 2014. ACCC chairman Rod Sims believes that the $A1.5bn deal has contributed to the rising cost of electricity, noting that the competition regulator had warned of this at the time. AGL is under growing scrutiny over its plans to shut down the Liddell power station in 2022. The Federal Government recently set a deadline of 90 days for AGL develop a plan to replace the ageing plant’s output of 1,000 megawatts.

CORPORATES
AGL ENERGY LIMITED – ASX AGL, MACQUARIE GENERATION, AUSTRALIAN COMPETITION AND CONSUMER COMMISSION, ORIGIN ENERGY LIMITED – ASX ORG, ENERGYAUSTRALIA PTY LTD, AUSTRALIA. DEPT OF THE PRIME MINISTER AND CABINET, AUSTRALIA. COMPETITION TRIBUNAL, VERTIUM ASSET MANAGEMENT, UBS HOLDINGS PTY LTD, ALCOA INCORPORATED

Turnbull’s power deal with AGL

Original article by David Crowe
The Australian – Page: 1 & 8 : 12-Sep-17

Prime Minister Malcolm Turnbull and Energy Minister Josh Frydenberg held talks with AGL Energy CEO Andy Vesey regarding the Liddell coal-fired power station on 11 September. Vesey agreed to a 90-day deadline to develop a plan to replace the ageing power station’s output. He will also put a proposal to the AGL board to sell the power station or keep it open for five years beyond its slated shutdown in 2022. The Australian ­Energy Market Operator has estimated that an extra 1,000 megawatts of electricity generation will be needed to offset the closure of Liddell.

CORPORATES
AUSTRALIA. DEPT OF THE PRIME MINISTER AND CABINET, AUSTRALIA. DEPT OF THE ENVIRONMENT AND ENERGY, AGL ENERGY LIMITED – ASX AGL, AUSTRALIAN ENERGY MARKET OPERATOR LIMITED, AUSTRALIAN LABOR PARTY, AUSTRALIAN GREENS, AUSTRALIA. OFFICE OF THE CHIEF SCIENTIST

$9bn power hit for big firms

Original article by Eli Greenblat, Damon Kitney
The Australian – Page: 1 & 4 : 7-Sep-17

National Australia Bank’s chief economist Alan Oster has forecast that higher energy costs will add 0.6 per cent to the headline inflation rate for the September quarter. Companies that are major energy users estimate that their electricity and gas costs will rise by $A9bn, which in turn will affect profit margins, jobs and investment. Meanwhile, AGL Energy has advised that it has made no commitment to sell its Liddell power station or keep it operating beyond the planned closure date of 2022. Prime Minister Malcolm Turnbull has claimed that AGL CEO Andy Vesey had indicated that the company would be open to selling the power station.

CORPORATES
NATIONAL AUSTRALIA BANK LIMITED – ASX NAB, AGL ENERGY LIMITED – ASX AGL, AUSTRALIA. DEPT OF THE PRIME MINISTER AND CABINET, AUSTRALIA. DEPT OF THE TREASURY, RIO TINTO LIMITED – ASX RIO, MINERALS COUNCIL OF AUSTRALIA, DELTA ENERGY PTY LTD, GLENCORE PLC, AUSTRALIAN PETROLEUM PRODUCTION AND EXPLORATION ASSOCIATION LIMITED, AUSTRALIAN LABOR PARTY, TOMAGO ALUMINIUM COMPANY PTY LTD, THE AUSTRALIAN INDUSTRY GROUP, PACT GROUP HOLDINGS LIMITED – ASX PGH, COSTA GROUP HOLDINGS LIMITED – ASX CGC, BLUESCOPE STEEL LIMITED – ASX BSL

Newcrest unscathed as NSW mine reopens

Original article by Peter Ker
The Australian Financial Review – Page: 16 : 24-Nov-15

Australian-listed Newcrest Mining has advised that problems with a mill at its Cadia gold mine in New South Wales have been resolved. The mill has resumed production after a 35-day shutdown and has returned to full capacity. Output in the September 2015 quarter had been affected by the shutdown, but Newcrest still expects to achieve its 2015-16 full-year production guidance of 2.4 million to 2.6 million ounces of gold.

CORPORATES
NEWCREST MINING LIMITED – ASX NCM, SHAW AND PARTNERS LIMITED, CITIGROUP PTY LTD