Olympic Dam gets a $40m injection

Original article by Cameron England
The Australian – Page: 16 : 4-Feb-25

A joint venture between Fluor Australia and Hatch has been awarded a major contract for the proposed expansion of BHP’s copper smelter and refinery at its Olympic Dam project. BHP’s procurement officer Rashpal Bhatti says the two companies that were selected for the $40m engineering, procurement and construction management contract have "significant shared experience" in delivering major projects. BHP expects to make a final investment decision on the expansion during the first half of the 2026–27 financial year.

CORPORATES
BHP GROUP LIMITED – ASX BHP, FLUOR AUSTRALIA PTY LTD, HATCH ENGINEERING

Miners face $150m hit from blackout

Original article by Matt Chambers
The Australian – Page: 17 & 27 : 4-Oct-16

OZ Minerals has advised that electric power is unlikely to be restored at its Prominent Hill mine in South Australia for at least another week, while its 2016-17 gold production forecast may not be met as a result. The recent state-wide power outage also halted production at BHP Billiton’s Olympic Dam mine and Arrium’s Whyalla steelworks. Meanwhile, the suspension of production at Nyrstar’s lead smelter at Port Pirie is believed to have contributed to a spike in the price of lead on the London Metal Exchange.

CORPORATES
OZ MINERALS LIMITED – ASX OZL, BHP BILLITON LIMITED – ASX BHP, ARRIUM LIMITED – ASX ARI, NYRSTAR AUSTRALIA PTY LTD, LONDON METAL EXCHANGE LIMITED, KORDA MENTHA AND COLLEAGUES PTY LTD